NHER 66166 (Monument record) - Undated ditch
The Norfolk Heritage Explorer is a filtered version of the Norfolk HER intended for casual research. Please contact us to consult the full record.
See also further guidance on using the Norfolk Heritage Explorer website.
Summary
Protected Status/Designation
- None recorded
Location
| Map sheet | TG13SW |
|---|---|
| Civil Parish | CORPUSTY AND SAXTHORPE, NORTH NORFOLK, NORFOLK |
Map
Full Description
February-March 2017. Geophysical Survey.
Magnetometer survey of site on possible route of Hornsea Project Three offshore wind farm onshore cable (GS06).
This site was one of 26 identified as a priority for examination due to their archaeological potential.
The survey identified nothing of definite archaeological interest. The most notable responses are a cluster of discrete positive anomalies at the southern edge of the site, although it is suggested these are potentially natural in origin.
Scattered discrete dipolar 'spikes' and larger areas of weak magnetic disturbance are probably the result of ferrous material on or close to the surface (most likely modern debris).
Information from draft report. Final version awaited.
P. Watkins (HES), 8 May 2025.
May 2018. Desk-based Assessment.
Environmental Impact Assessment of the potential impacts of the proposed Hornsea Project Three offshore wind farm on the historic environment. This study incorporated the results of an initial walkover survey and the first phases of geophysical survey.
See relevant chapter of Environmental Statement and associated appendices for further detail (S1).
P. Watkins (HES), 8 May 2025.
February-June 2022. Trial Trenching.
Evaluation of site on proposed route of Hornsea Project Three offshore wind farm onshore cable (P1TT06; Trench 29-33).
The majority of the five trenches excavated at this location revealed no archaeologically-significant remains, with only an undated north-west to south-east aligned ditch recorded. No finds were recovered.
Information from draft report. Final version awaited.
P. Watkins (HES), 8 May 2025.
Associated Sources (1)
- <S1> SNF101788 Unpublished Contractor Report: [anonymous]. 2018. Hornsea Project Three Offshore Wind Farm. Environmental Statement: Volume 3, Chapter 5 - Historic Environment. RPS Group.
Site and Feature Types and Periods (1)
Object Types (0)
Related NHER Records (0)
Record last edited
May 8 2025 12:51PM